REPRESENTATIVE  PROJECTS

 GEOTECHNICAL INVESTIGATION AND SOIL/WATER STUDIES

                                                       

DATE

OWNER/CLIENT

CONTRACT

BUDGET ($)

PROJECT/LOCATION

ACTIVITY

1998

Hamed Al-Khalid

6,000

Jeliaa Beach Resort

Geotechnical Investigation

1998

Al-Imad Real Estate Co.

9,000

Laila Residential Complex

Geotechnical Investigation

1998

MPW/Asian Engineering

3,000

Chest Diseases Hospital

Geotechnical Investigation

1998

PAHC

18,000

Jleib Al-Shuyoukh, Block 2

Sector No.14 & 26  Tender

MNRS/14/1993

Geotechnical Investigation

1998

Ghassan Al-Khalid

7,500

Earth Works Specifications

Al-Zour Beach

Geotechnical Investigation

1999

Civil Aviation/Qualimetrics

4,000

Different areas in Kuwait

Geotechnical Investigation

2000

Civil Aviation/Qualimetrics

4,000

Different areas in Kuwait

Geotechnical Investigation

2001

EPA/Kuwait University

90,000

Investigation of Solid Waste area at Al-Qurain

Geotechnical Investigation

and hydrogeological study

2001

PEAAT/PACE

10,500

PEAAT Al-Ardia School

Geotechnical Investigation

2002

MOH/Langdon Wilson Int’l

4,000

Cardiac Annex/Shuwaikh

Geotechnical Investigation

2002

MPW/UGC

30,000

Mishref Pump Station/Mishref

Instrumented full ssscale pump test

2002

MPW/COWI

36,000

Subiya Causeway / Subiya

Supervisor for field/laboratory testing programs

 

   REPRESENTATIVE PROJECTS

  GEOTECHNICAL INVESTIGATION AND SOIL/WATER STUDIES

                                                              

DATE

OWNER/CLIENT

CONTRACT

BUDGET ($)

PROJECT/LOCATION

ACTIVITY

2002

KCPC

9,000

Ashaab Health Club

Plate load testing program

2002

Al-Bannai/PWH

8,000

Ardiya, Farwania

Geotechnical Investigation

2003

Club of Hearing Impaired/PACE

3,000

Doha, Hearing Impaired club

Geotechnical Investigation

Drilling BH, SPT, Lab Testing

2004

La' Ala Al-Kuwait Co.  Infrastructure

100,000

Khairan Pearl / Khairan

Geotechnical Investigation

SPT, CPT, Lab Testing

2003/2004

La' Ala Al-Kuwait Co.

500,000

Khairan Pearl / Khairan

Establishing Soil Lab. for Earthwork/ Rock testing/ Concrete testing on site

2004

Kuwait Municipalty/PACE

5,000

Municipality Car Park

Geotechnical Investigation

2004

Al-Mal real Estate / Ahmadia

5,000

Dhow Tower

Geotechnical Investigation

3D Foundation Model

2004

Perini Corp.

US Army  CORP. of Engineers

80,000

Nasiriya Power Station

Geotechnical Investigation

2004

PAAET/PACE

5,000

PAAET – Sabahiya

Geotechnical Investigation

2004

Sadeeq Co.op/ PACE

6,000

Sadeeq Coop. – South Sura

Geotechnical Investigation

2004

La' Ala Al-Kuwait Co.

35,000

Industrial area – Khiran Pearl City

Geotechnical Investigation

2004

La' Ala Al-Kuwait Co.

6,000

Water Tower -  Khiran Pearl City

Geotechnical Investigation

REPRESENTATIVE PROJECTS

 GEOTECHNICAL INVESTIGATION AND SOIL/WATER STUDIES

 

DATE

OWNER/CLIENT

CONTRACT

BUDGET ($)

PROJECT/LOCATION

ACTIVITY

2004

Ahmadiah

6,000

Khiran Pearl City

Borehole drilling

2004

Panarab

9,000

Geotechnical Investigation for Asian Olympic Council Complex

Geotechnical Investigation

 

-Drilling in soil to 40m BGL , soil sampling and testing

- Geotechnical material assessment for the proper foundation, excavation and dewatering systems.

2004

Ahmadiah

4,000

Geotechnical Investigation for Residential Towe at Dasman – Sharq

Geotechnical Investigation

 

 

2005

COWI

31,500

Subiya Causeway / Subiya

Supervisor for field/laboratory testing programs

2005

Panarab

18,000

Arraya Tower II / Sharq

Deep drilling / Test pressuremeter, cross hole test

2005

La' Ala Al Kuwait

10,000

Khiran Pearl City

Plate Load Test

2005

La' Ala Al Kuwait

8,000

Khiran Pearl City

Ground water monitoring wells

  REPRESENTATIVE PROJECTS

 TOPOGRAPHIC ENGINEERING, BATHIMETRIC/HYDROGRAPHIC SURVEYS


DATE

OWNER/CLIENT

CONTRACT

BUDGET ($)

PROJECT/LOCATION

ACTIVITY

2000

MPW

25,000

MPW/

Sabah Al-Nasser

Topographic mapping at

1/2000 scale

2000

MPW

13,000

MPW

Fintas Agricultural Area

Topographic mapping at

1/2000 scale

2000

Gulf Consult

20,000

Nuwaseeb Border Post

Topographic mapping at

1/2000 scale

2000

ASCO

50,000

Industrial Areas (Subhan, Sulaybia, Amgara & Doha)

Topographic mapping at

1/2000 scale

2000

Gulf Consult

17,000

Fahaheel coastal shore

Bathymetric survey of area

 2km by 1km

2000

Mesila Beach Hotel

4,500

Messilah Beach Hotel

Bathymetric survey of area

 500m by 500m

2000

First Kuwaiti Co.

4,500

Private Marine

At Mahbula

Bathymetric survey of area

 500m by 500m

2000

Pepsi Cola

16,000

Pepsi Cola I

Subhan

Survey (Plans & elevations)

2000

Gulf Consult

9,000

Al-Mula Garage

 Shuwaikh

Survey (Plans & elevations)

2001

MEW

23,000

Pipiline

From Mina Abdulla to Wafra

 

Topographic mapping at

1/2000 scale

2001

Equestrian Club

8,000

Hunting

Equestrian Club

Topographic mapping at

1/2000 scale

       

REPRESENTATIVE  PROJECTS

TOPOGRAPHIC ENGINEERING, BATHIMETRIC/HYDROGRAPHIC SURVEYS

                                                   

DATE

OWNER/CLIENT

CONTRACT

BUDGET ($)

PROJECT/LOCATION

ACTIVITY

2001

First Kuwaiti Co.

3,000

Fintas Project

Bathymetric survey

2001

First Kuwaiti Co.

7,000

Private Marine

At Salmiya

Bathymetric survey of area

 500m by 500m

2001

National Council of Art

10,000

Shrqieh Girls School

Survey (Plans & elevations)

2001

EPA/Kuwait University

3,000

Solid Waste area

At Al-Qurain

Topographic mapping at 1/1000 scale

2003

Kharafi / SSH

3,000

Al-Qurain Solid waste area

Topographic mapping at 1/1000 scale

2004

MOD / Al-JAWAD

5,000

JAHRA CAMP

Topographic mapping

2004

La' Ala Al-Kuwait Co.

20,000

Khairan Pearl

Pathymetric /Topographic Survey

2004

PAAET / PACE

4,000

PAAET – Sabahiya

Topographic Survey

2004

Sadeeq Co.op / PACE

4,000

Sadeeq Co.op – South Sura

Topographic Survey

2004

Panarab

3,000

For Asian Olympic Council Complex – Salmya

Topographic Survey

2005

Panarab

1,000

Al Anwar Center

Topographic Survey

 

 

 

 

 

 

 

 

 

          

REPRESENTATIVE PROJECTS

STRUCTURAL EVALUATION AND CONCRETE REPAIR DESIGN

                                                 

DATE

OWNER/CLIENT

CONTRACT

BUDGET ($)

PROJECT/LOCATION

ACTIVITY

1992

KNPC/RPT

22,500

KNPC Refineries Restoration

Project

Structural Testing

1996

Ahmed Al-Wazzan

5,000

Private Villa at

Khaldiya

Detail Structural Survey

& Remedial Measures for

Concrete Deterioration

1997

KNPC

7,000

Modernization of 3 reactors

Shuaiba

Structural Survey &

Damage Assessment

1997

KNPC

15,000

Lube Oil Factory

Shuaiba

Structural Survey &

Evaluation of Industrial

Tanks

1998

Kuwait Club/Burhan Co.

6,000

VIP Hall & Duwaniah at

Soccer Hall Stadium

Kuwait Sports Club

Stability Analysis &

Design of Support System

 

1998

MPW/S.S.H.

9,000

Guest Palace Bayan Palace -

Phase II

Structural Survey &

Crack mapping

1998

DGCA

3,000

Rehabilitation for Kwt. Airport

Terminal Building

Structural Assessment

Program

1998

PIC

12,000

Salt and Chlorine Plant

PIC - Shuaiba

Structural Survey &

Damage Assessment

1998

National Council of Culture,

Arts and Literature

7,000

Dickson House 

Restoration

Structural Survey &

Damage Assessment

1998

KNPC

15,000

Lube Oil Plant

 

Structural Survey & Damage

Assessment of Tank Farm

REPRESENTATIVE  PROJECTS

 STRUCTURAL EVALUATION AND CONCRETE REPAIR DESIGN

           

DATE

OWNER/CLIENT

CONTRACT

BUDGET ($)

PROJECT/LOCATION

ACTIVITY

2000/2001

Civil Aviation/Qualimetrics

60,000

Weather Station

in Kuwait

Structural Survey and

assessment of existing structures

2001

Al-Ostoura Co.

10,000

Structural Design

Dana Center

Structural survey and steel structural support of existing structure including design of car rotating display platform

2002

NCCAL/Modern System

2,400

Design of support system to the damaged Al-Qurain       Al-Shuheda House

Design of steel structural support

2002

MOH/Langdon Wilson Int’l

12,000

Design of reinforced concrete structure CARDIAC ANNEX Shuwaikh

Structural design and detail of reinforced concrete structure

2002

VIP Chateau Health Club/ Dourwaza Office

4,000

VIP Chateau Health Club Bneid AlGar

Structural survey as built condition

2002

Al-Bannai/Private Sector

3,000

Private Building In Salwa

Evaluation of Building movement and cracks

2003

DGCA

1,50,000

2002-2003/15

Testing Evaluation Fire effected Concrete structure

Structural Testing, Evaluation, Capacity analysis, Structural analysis, Design of repair scheme of concrete member, Supervising concrete repair, Structural load Test.

 

  REPRESENTATIVE  PROJECTS

 STRUCTURAL EVALUATION AND CONCRETE REPAIR DESIGN

     

DATE

OWNER/CLIENT

CONTRACT

BUDGET ($)

PROJECT/LOCATION

ACTIVITY

2003

DGCA/Arab Center

2,000

Water Tank/ Airport

Structural Analysis and Evaluation

2003

Al-Nafisi/ Ahmadiya

12,000

Arraya Tower, Sharq

Structural Analysis

2003

Ahmadiya

3,000

Salhiya Car Park

Survey of Dynamic Impact on

Concrete Structure.

2004

DGCA

300,000

Testing, evaluation and assessment of Block B    and C

3D Simulation of the existing terminates and evaluation of structural capacity

2004

DGCA

21,000

Testing, evaluation and assessment of Block F    and G

3D Simulation of the existing Blocks F & G terminates and evaluation of structural capacity

2004

MPW / Horizon Enterpirzes

12,000

Structural analysis & repair design for Ministry complex car park area

Structure analysis & repair design

2004

Al Oustura

1,500

For Al Oustura – Stair Case Structure Assessment

Structural assessment & Steel design

2004

Commercial Bank of Kuwait

3,000

For CBK – KIA Br.

Structural Analysis.

2005

Al Jawad

18,000

Jassim Al Bashar Dahia Villa

Structural Analysis.

2005

Al Maousherji Catering Co.

36,750

McDonald – KIA Br.

Erection of McDonald's Structural support of the frame under McDonald's Restaurant at KIA

 

   REPRESENTATIVE  PROJECTS

  GEOTECHNICAL DESIGN FOR DEEP FOUNDATION

 

DATE

OWNER/CLIENT

CONTRACT

BUDGET ($)

PROJECT/LOCATION

ACTIVITY

1998

MPW/UGC

1,500

Sewage Renovation Phase III

Part A, Kuwait City Pumping

Contract SE/18/96-97

Checking Dewatering System

and Design New System

1998

Al-Sharq Co.

3,000

Al-Shaya Warehouse

Shop No.5

At Shuwaikh

Structural assessment of Slab

on grade

2000

Al-Imad Real Estate/ Jaberco

1,500

Tower crane pile foundation

Salmiya

Design of pile and cap

2002

MPW/UGCC

6,000

Mishref Pump Station

Mishref

Design of dewatering system

2002

MPW/UGCC

6,000

Mishref Pump Station

Mishref

Design of slope stability

2002

MPW/UGCC

15,000

Mishref Pump Station

Mishref

Full scale instrumented pump test

2003

MEW/ HYUNDAI

5,000

Shamiya S/S

Design of Raft Foundation

Concrete Structural Design of raft foundation of raft on pile by FEM

2004

MPW/ Al-Aswar Technology

30,000

Design of pile and footing

Concrete Structural Design of pile and footing for telecommunication tower

REPRESENTATIVE  PROJECTS

GEOTECHNICAL DESIGN FOR DEEP FOUNDATION

 

DATE

OWNER/CLIENT

CONTRACT

BUDGET ($)

PROJECT/LOCATION

ACTIVITY

2004

National Khorafi / Al-Aswar Technology

100,000

Design of footing

Concrete Structural Design of  footing for telecommunication tower

2004

PERINI CORP.

US ARMY CORP. of Engr's

30,000

Nasiriya / Iraq

Design of Driven piles and capping for machinery foundations

2004

Mishref Company / Ghannam & Al sayegh

3,000

Design of piling foundation for tower crane  - Mishref

Detail design of precast driving piles with cap

2005

DGCA / ALMOS

24,000

AWOS / All over Kuwait

Designing Foundation for different instrumentation and weather stations

 

 

 

 

 

 

 

 

 

 

 

REPRESENTATIVE PROJECTS

 MARINE GEOTECHNICAL INVESTIGATION

 

DATE

OWNER/CLIENT

CONTRACT

BUDGET ($)

PROJECT/LOCATION

ACTIVITY

1996

National Real Estate Co./KEO

24,000

Al-Sharq Water Front

Kuwait City

Offshore Soil Investigation

1998

KNPC/Mouchel International

300,000

MAA-Refinery New Oil Jetty

 And Topside Facilities

Geotechnical Study

1999

United Real Estate Co.

30,000

Salmiya Water Front Proj.

Kuwait City

Water Quality & Testing of

Materials

2001

Civil Aviation/Qualimetrics

30,000

AWOS at different locations in Kuwait

Checking the existing AWOS

marine stations

2002

MPW/COWI

9,000

Subiya Causeway

Subiya - Kuwait

Geotechnical supervision on site

2004

La'Ala Al Kuwait Co.

20,000

Drilling in Khor Al'Ama in Khairan

Geotechnical Investigation for cap rock and marine sedimentation

 

 

 

 

 

 

REPRESENTATIVE  PROJECTS

CONSTRUCTION MATERIAL TESTING (ITLS)

           

DATE

OWNER/CLIENT

CONTRACT

BUDGET ($)

PROJECT/LOCATION

ACTIVITY

1993

KAC/Mohamed Al-Rajhe Co.

13,500

Hangar 747 Ground Slabs

Kuwait Airport

Structural & Material

Testing

1993

Al-Nazaer Co.

3,000

Assessment of Fire Damage

Concrete Structure, at Subhan

Material Testing

1994/95

KNPC/CONCO

20,000

Small Boat Harbour Project,

Mina Abdullah

Materials Testing &

Quality Control

1995

KOC/The Ralph Parsons

22,500

KOC Ex-Main Office

Ahmadi

Material Strength Testing &

Structural Survey

1997

Al-Awqaf

30,000

Testing, evaluation and analysis

of Historical Mosque

Material Testing &

Structural Survey

1999

U.S. Embassy/H.Behbehanni

10,000

Constr. of Housing Project

ITLS, Material Testing,

Topographic Survey

2000

Private/Kuwait-German Ready Mix 

1,500

Evaluation of hardened concrete/South Surra

Material testing

2001

PEAAT/Alghanim Int’l.

1,500

PEAAT Project/

Shuwaikh

Checking the hardened concrete

2001

Private/A-Watania Ready Mix 

3,000

Evaluation of structure/South Surra

Structural analysis & material testing

2002

National Museum/PACE 

13,500

Renovation of BLDG#3             Kuwait National Museum

Structural survey & Material testing

2003

KCPC

4,000

Al-Shaab Club

PLT& other material Testg.

 

 

 

 

 

 

REPRESENTATIVE  PROJECTS

  CONSTRUCTION MATERIAL TESTING (ITLS)

                                              

DATE

OWNER/CLIENT

CONTRACT

BUDGET ($)

PROJECT/LOCATION

ACTIVITY

              

2004

 

 

 

2005

 

 

 

 

La’ Ala’ Al-Kuwait

 

 

 

 

La’ Ala’ Al-Kuwait

 

 

 

 

 

360,000

 

 

 

360,000

 

 

 

 

Material Testing  ITLS , Khairan

Providing Mobile Lab on site for concrete, soil, material sediments.

Earth work/concrete rock testing includes:-

- soil classification test ASTM, BS

 - soil strength tests, ASTM, BS

- testing Beach Sand Sampling for cleaning oerobic Bacteria and fine silt material from Beach SAND.

- Armour Rock testing , channel reinforcement rock testing.

- Environment testing for H2s, Odor water quality

  

REPRESENTATIVE  PROJECTS

GEOTECHNICAL/STRUCTURAL / ENVIRONMENTAL INSTRUMENTATION

 

 

DATE

 

OWNER/CLIENT

 

CONTRACT

BUDGET ($)

 

  PROJECT/LOCATION

 

ACTIVITY

1995

MEW/Kuwait Institute of

Scientific Research

132,000

Pilot Drainage Project

 Sabah Al-Salem/Khifan and

 Shamiya

Installation of 75m deep magnetic

and rod extensometer, pressure

transducers, water level sensors,

data loggers and providing maintenance services

(Soil instruments and Geocon)

1995

Kuwait Real Estate Co.

48,000

Salmiya Market Ground

Preloading Test - Salmiya

Installation of magnetic

extensometers, settlement plates, pneumatic piezometers, casagrande piezometers and monitoring services

1997

Nouf Real Estate Co./

Oha Engineering

48,000

Salmiya Market Monitoring

 of Preloading Process

Installation of casagrande piezometers and settlement plates

1998

Nouf Real Estate Co./

Oha Engineering

45,000

Salmiya Market Monitoring

 of Preloading Process

Monitoring of Settlements and PWP. during preloading

2000/2001

EPA/Kuwait University

90,000

Solid Waste Investigation/

Al-Qurain

Installation of Magnetic extensometers/Pneumatic piezometers/Casagrande Piezometers, monitoring samples

2002

MPW/UGCC

30,000

Mishref Pump Station

Fully instrumented pump test for deep dewatering system design

2004

Al Mal Tower / Ahamadia

3,000

Writing proposal for Tilting and Excavation  - Sharq

Writing technical proposal

 

 

 

 

 

 REPRESENTATIVE  PROJECTS

 GEOTECHNICAL/STRUCTURAL / ENVIRONMENTAL

INSTRUMENTATION

 

               

DATE

OWNER/CLIENT

CONTRACT

BUDGET ($)

PROJECT/LOCATION

ACTIVITY

                                                             

2004

DGCA

150,000

ATCT tower instrumentation – KIA (Proposal)

Instrumentation for tilt and Earth Quick

2004

PAHC / Golden Shaheen

Proposal

Arifjan, Developing residential new area.

 - Gophysical survey by seismic refractions, gravimeter, resistivitiy and tomography. Noise and Air pollution survey

 

 

REPRESENTATIVE PROJECTS

ENVIRONMENT TESTING & EIA

                                                              

DATE

OWNER/CLIENT

CONTRACT

BUDGET ($)

PROJECT/LOCATION

ACTIVITY

2002

EPA/KU

90,000

Study Evaluation of municipal solid waste, Al-Qurain Area

1.      Drill borehole in highly contaminated hazardous field.

2.      Collecting hazardous samples GW/ water/Soil

3.      Monitoring GWL and developing the simulation ground water motel 3D

4.      Full scale pump test

5.      Instrumental preloading trial

6.      CPT on MSW

7.      Topographic survey

2003

Kharafi/SSH

45,000

Preparing technical/ Financial specification for Al-Qurain MSW area.

Design the technical    financial requirement for treatment /rehabilitation

2003

MPW/UGC

30,000

Mishref Pump Station

Design of dewatering system to eliminate H2S

2004

PIC / RIMKUS

3,000

UREA Plant Sewer, Shuaiba

Pit design of sewer Pit CAPS baskets

2003/2004

Kuwait Municipality / SSH

50,000

Qurain land fill rehabilitation program

Writing environmental proposal for land fill area

 

REPRESENTATIVE PROJECTS

ENVIRONMENT TESTING & EIA

 

 

DATE

OWNER/CLIENT

CONTRACT

BUDGET ($)

PROJECT/LOCATION

ACTIVITY

2003/2004

Kuwait Municipality / SSH

50,000

Qurain land fill rehabilitation program

Writing environmental proposal for land fill area

 - Design program to study Lithology, Hydrogeology for the area.

 - Design concept for liner cover system

 - Design concept for improving soil layer system

 - Design concept for Gas management and control system

 - Design concept for Leachate control & management system

2004

PAHC – Golden Shaheen

Proposal

Proposal for Studying the Noise, Control and Air pollution for Arifjan area and impact of new residential area on the Direct Environment

 - Design study program to control Noise immersion and Air quality in the area